[2022] New E-ACTCLD-21 exam dumps Use Updated SAP Exam
Verified E-ACTCLD-21 Dumps Q&As - E-ACTCLD-21 Test Engine with Correct Answers
E-ACTCLD-21 Exam Certification Details:
| Exam: | 40 questions |
| Duration: | 90 mins |
| Level: | Associate |
SAP E-ACTCLD-21 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Agile Project Delivery 8% - 12% | Describe how the project team prepares release and sprint plans, and the structure and key activities in each sprint. Discuss key techniques used in agile projects
|
| Agile Project Planning > 12% | Describe the agile project roles and responsibilities and the preparation of the project including the planning, estimation, user story mapping and construction of backlog
|
| SAP Activate Overview > 12% | Define factors influencing SAP Activate, its purpose and place among other frameworks
|
SAP E-ACTCLD-21 Exam Description:
The "SAP Certified Specialist - SAP Activate for Cloud Solutions Project Manager" certification exam verifies that the candidate has the knowledge required in the area of SAP project management. This exam validates whether SAP Cloud-focused project managers have advanced business skills and the ability to apply methodologies and tools. Aside from advanced communication and presentation skills, this certificate also verifies that the project manager has skills to manage internal and external stakeholders, basic knowledge of change management processes, and communicating these processes to others. This exam validates that project manager can successfully manage the end-to-end transition of the project from Sales to Realization, can develop roadmaps for project execution, and understand testing and quality management. In particular for SAP Cloud-related projects, the exam verifies that the Project Manager can apply the SAP Activate Methodology.
NEW QUESTION 23
In SAP Activate, what replaces the detailed Blueprint from ASAP? Please choose the answer.
- A. Fit/Gap Workshops
- B. Value Determination
- C. Custom Extension management
- D. Business Process Mapping
Answer: A
NEW QUESTION 24
What does a cutover involve?
- A. Closing quality gate
- B. Switching productive business operations from one system to another
- C. Transporting new product increment in the development system
- D. Presenting completed User Story to key users
Answer: B
NEW QUESTION 25
SAP Activate uses concepts, ceremonies, roles introduced by SCRUM methodology and expands them with Solution Implementation specifics.
- A. True
- B. False
Answer: A
NEW QUESTION 26
Which of the following are part of the 10 SAP Quality Principles? Note: There are 2 correct Answers to this question.
- A. Plan one phase at a time.
- B. None
- C. Start scoping early.
- D. Achieve production readiness.
- E. Use standard functionality.
Answer: C,D
NEW QUESTION 27
What is a difference between the SAP Activate methodology for a new implementation of SAP S/4HANA cloud edition and a new implementation of SAP S/4HANA on-premise?
- A. For on-premise, there is an additional Q-Gate for system installation
- B. For on-premise, there are additional deliverables for the system setup
- C. For the cloud edition, there is an additional Q-Gate for integration with on-premise systems
- D. For the cloud edition, there is an additional work stream for integration with on-premise systems
Answer: B
NEW QUESTION 28
Working in an Agile approach, what should your planning look like at the beginning of the Realize phase?
- A. Project scope and planning are compelted and final
- B. Go-live scope is fixed on the first of January the following year
- C. User Stories are in Ready state for only the first 2 to 3 sprints
- D. Timelines of the sprint many differ dues to the workload
Answer: C
NEW QUESTION 29
Which artifacts are part of the Solution Adoption workstream? Note: There are 3 correct Answers to this question.
- A. Project Plan
- B. Change Management Roadmap
- C. Learning Content
- D. End User Learning Needs Analysis
- E. Detailed Design - Business Process
Answer: B,C,D
NEW QUESTION 30
What does the side-by-side extensibility option mean?
- A. Have two SAP S/4HANA instances-one for standard code, and another for customer developments
- B. Transfer reporting to BW/4HANA
- C. Extensibility based on the SAP cloud platform and published APIs
- D. Context-aware SAP S/4HANA extensions, focused on tight integration
Answer: C
NEW QUESTION 31
Your are defining the test strategy for your project. What would you include in a Scope of Integration test?
- A. the functionality of end-to-end business processes
- B. the connectivity between database and application servers
- C. the functionality of modular processess
- D. the network communication
Answer: A
NEW QUESTION 32
Your project is performing some high-level planning for a System Conversion journey from SAP Business Suite to SAP S/4HANA on-premise edition.
What is the sequence of selected key deliverables across the project phases? Please choose the answer.
- A. 3rd option
a. Detailed system Assessment
b. Code Adjustment
c. Validation of Migration
d. Production Readiness Check - B. 1st option
a. Code adjustment
b. Detailed System Assessment
c. Production Readiness Check
d. Validation of Migration - C. 4th option
a. Detailed system Assessment
b. Production Readiness Check
c. Code Adjustment
d. Validation of Migration - D. 2nd option
a. Production Readiness Check
b. Detailed system Assessment
c. Code Adjustment
d. Validation of Migration
Answer: A
NEW QUESTION 33
Which of the following scenarios are enabled for the "selective data transition" Transition Path with the SAP landscape transformation tool? There are 3 answers to this question.
- A. Consolidation through online data replication
- B. Security migration
- C. System consolidation
- D. Extraction of business units
- E. System upgrade
Answer: A,C,D
NEW QUESTION 34
What do you do during an iterative approach to build a solution? Please choose the answer.
- A. Deliver a prototype of the solution
- B. Build the solution module by module
- C. Provide a working solution only at the end of the release
- D. Include frequent inspection check-points
Answer: D
NEW QUESTION 35
Which of the following is not about Fit/Gap Analysis (done during Explore Phase)? There are 2 answers to this question.
- A. Minimize the needs for rework during realization.
- B. Prioritize delta requirement and gaps.
- C. Drive towards adopting customers processes.
- D. Validate pre-activate and pre-assembled solution in the development system.
Answer: C,D
NEW QUESTION 36
What is one of the main benefits of SAP Cloud ALM for operations that helps customers to improve efficiency?
- A. Automation
- B. Integration optimization
- C. Workflow management
- D. Business process improvements
Answer: A
NEW QUESTION 37
In which phase of the SAP Activate methodology does the team complete the Cut-over Rehearsal?
- A. Prepare
- B. Realize
- C. Deploy
- D. Explore
Answer: C
NEW QUESTION 38
What is the purpose of the scrum board?
- A. To show the functional breakdown of the solution scope
- B. To visualize team progress
- C. To document the results of the integration test
- D. To manage the resource load
Answer: B
NEW QUESTION 39
......