[Nov-2021] C_ACTIVATE12 Dumps are Available for Instant Access using Actual4Exams [Q67-Q87]

Share

[Nov-2021] C_ACTIVATE12 Dumps are Available for Instant Access using  Actual4Exams 

C_ACTIVATE12 Dumps 2021 - New SAP C_ACTIVATE12 Exam Questions


Understanding valuable and specific pieces of Certified Associate - SAP Activate Project Manager

The going with will be discussed in SAP C_ACTIVATE-12 dumps:

  • Factors affecting SAP Activate
  • Aspects to be considered for inciting SAP Fiori as an element of your execution
  • System Conversion for SAP SAP HANA
  • SAP Activate Overview
  • Workstreams personally
  • SAP Activate personally
  • Workstreams well
  • Implement SAP HANA Cloud
  • Aspects to be considered for establishing SAP Fiori as a segment of your execution
  • Implement SAP HANA On-Premise
  • Landscape Transformation for SAP SAP HANA
  • Scope and Goals of ACT100
  • Implement SAP HANA Cloud
  • Landscape Transformation
  • SAP Activate well overall
  • SAP Activate Overview
  • Factors affecting SAP Activate
  • SAP HANA On-Premise
  • Conversion for SAP SAP HANA

 

NEW QUESTION 67
What SAP Cloud Platform integration tool would you use to integration SAP S/4HANA Cloud and SAP S/4HANA on premise?

  • A. SAP Cloud Platform, API Management
  • B. SAP Cloud Platform, Open Connectors
  • C. SAP Cloud Platform, Connectivity
  • D. SAP Cloud Platform, Cloud Integration

Answer: C

 

NEW QUESTION 68
Via which media does SAP provide ready-to-run systems for SAP S/4HANA deployment? There are 2 correct answers to this question.

  • A. Blu-ray disks
  • B. SAP App centre
  • C. SAP Solution Builder tool
  • D. SAP cloud appliance library

Answer: A,D

 

NEW QUESTION 69
What is the basis for approving work results (signing act of acceptance) on a project phase level?

  • A. Scrum of scrums meeting decision
  • B. Definition of done for user story
  • C. Definition of ready for sprint
  • D. Agreed and met acceptance criteria within quality gate

Answer: D

 

NEW QUESTION 70
Which of the following SAP S/4HANA Landscape Transformation options are enabled? There are 3 correct answers to this question.

  • A. System Upgrade
  • B. Migration of selected applications
  • C. System consolidation
  • D. Security Migration
  • E. Migration of business unit

Answer: B,C,E

 

NEW QUESTION 71
Which of the following are levels in the structure of an SAP Best practices solution package? There are 2 correct answers to this question.

  • A. Business process scenarios
  • B. Scope items
  • C. Building blocks
  • D. Configuration guides

Answer: B,C

 

NEW QUESTION 72
What are some characteristics of the Quality system?

  • A. Configurable system during implementation
  • B. Used for quality assurance check of business processes during quarterly upgrades
  • C. Decommissioned 30 days after Production system provisioning
  • D. Used to run your business in SAP S/4HANA Cloud

Answer: A,B

 

NEW QUESTION 73
What tool provides sizing estimations for the "System Conversion" transition path?
Please choose the correct answer.
Response:

  • A. Scope and Effort Analyzer
  • B. SAP Readiness Check
  • C. SAP Transformation Navigator
  • D. SAP Best Practices Explorer

Answer: B

 

NEW QUESTION 74
Which of the following scenarios are enabled for the "selective data transition" Transition Path with the SAP landscape transformation tool? There are 3 correct answers to this question.

  • A. Extraction of business units
  • B. System upgrade
  • C. System consolidation
  • D. Consolidation through online data replication
  • E. Security migration

Answer: A,C,D

 

NEW QUESTION 75
What is a benefit of using Guided Configuration instead of the Implementation Guide?
Please choose the correct answer.
Response:

  • A. It ensures configuration is done using SAP Solution Manager
  • B. It eliminates the need for Content Lifecycle Management
  • C. It ensures SAP updates do NOT conflict with customer configurations
  • D. It eliminates the need to generate transport requests for configuration settings

Answer: C

 

NEW QUESTION 76
What must you do when you implement SAP Business Suite On-Premise with SAP Best Practices?
Please choose the correct answer.
Response:

  • A. Activate and apply SAP Best Practices with SAP Solution Manager
  • B. Assemble and apply SAP Best Practices to the system
  • C. Activate and apply SAP Best Practices content with the self-service configuration UI
  • D. Apply SAP Best Practices with the Configure your Solution application

Answer: A

 

NEW QUESTION 77
Which of the following content best outlines the sequence of testing within the application Design and configuration workstream in the realize phase?

  • A. integration test
    User acceptance test
    String test
  • B. string test
    User acceptance test
    Integration test
  • C. string test
    Integration test
    User acceptance test
  • D. data migration
    String test
    User acceptance test

Answer: C

 

NEW QUESTION 78
What tool provides guidance on replacing custom code developed for SAP ERP with SAP S/4HANA functionality for the system conversion?

  • A. Software update manager with database migration option
  • B. Software provisioning manager
  • C. Simplification item check (Si-check)
  • D. SAP code inspector

Answer: C

 

NEW QUESTION 79
What is a key characteristic of SAP Activate for new implementations of S/4HANA cloud edition?
Please choose the correct answer.
Response:

  • A. Limited involvement of business stakeholders
  • B. Design-based
  • C. Start with executable content
  • D. Waterfall approach

Answer: C

 

NEW QUESTION 80
In which SAP Activate Methodology phase is the Experience Trial accessed by customers?

  • A. Explore
  • B. Discover
  • C. Prepare
  • D. Realize

Answer: B

 

NEW QUESTION 81
What types of extensibility are supported directly in the SAP S/4HANA Cloud solution?

  • A. Classic Extensibility
  • B. Managed Extensibility
  • C. In-App (Key User) Extensibility
  • D. Side-by-Side Extensibility

Answer: B,C

 

NEW QUESTION 82
Working in an Agile approach, what should your planning look like at the Beginning of the realize phase?

  • A. Project scope and planning are completed and final
  • B. Timelines of the sprint may differ due to the workload
  • C. User stories are in a ready state for NO more than the first three sprints
  • D. Go-live scope is fixed on the first of January the following year

Answer: C

 

NEW QUESTION 83
What are the responsibilities of the Product Owner in release and sprint planning?
There are 2 correct answers to this question.
Response:

  • A. Prioritize backlog user stories by business priority
  • B. Estimate the backlog user stories
  • C. Analyze the functional and technical dependencies between the user stories
  • D. Define objectives for each release

Answer: A,D

 

NEW QUESTION 84
What is the most granular level of the methodology you can view in the SAP Roadmap Viewer?
Please choose the correct answer.
Response:

  • A. Scenario
  • B. Phase
  • C. Deliverables
  • D. Task

Answer: D

 

NEW QUESTION 85
What are some responsibilities of customer key users after go-live of an SAP S/4HANA Cloud project?

  • A. Manage Users and Task Assignment.
  • B. Responsible for inspection and approval of results and of the overall project.
  • C. Search for solutions and process incidents from end users directly andwhen necessary, request help from SAP.
  • D. Monitor internal/external communications such as printers and integration with third-parties.
  • E. Complete the implementation activities as assigned.

Answer: A,C,D

 

NEW QUESTION 86
Which key activities does the Guided Configuration support you with?
There are 3 correct answers to this question.
Response:

  • A. Train new users
  • B. Testconfigured processes
  • C. Create test data
  • D. View solution scope
  • E. Manage roles of configuration users

Answer: A,B,E

 

NEW QUESTION 87
......

SAP C_ACTIVATE12 Exam Practice Test Questions: https://www.actual4exams.com/C_ACTIVATE12-valid-dump.html