NEW QUESTION # 86
What is performed as part of the recommended risk management procedure?
- A. Information about risks to the projects is sent to project stakeholders
- B. Risk management practices are reviewed to ensure that they are performed effectively
- C. A budget to investigate issues is allocated
- D. Conflicts between the project and the programme board are resolved
Answer: C
Explanation:
Explanation/Reference:
Reference https://www.greycampus.com/opencampus/prince-2-foundation/prince2-risk-management- procedure
NEW QUESTION # 87
Which is a purpose of the Risk Register?
- A. Describe the risk management techniques and standards to be applied to the project
- B. List the responsibilities for achieving an effective risk management procedure
- C. Act as a central record of information relating to the identified risks for the project
- D. Act as a repository for informal issues
Answer: C
NEW QUESTION # 88
What needs to be in place to ensure effective issue and change control?
- A. Manage by exception
- B. Quality planning
- C. Configuration management system
- D. Information needs for stakeholders
Answer: C
NEW QUESTION # 89
Where should a team manager look for information about the quality required for a product?
- A. Product description
- B. Team plan
- C. Quality management approach
- D. Project initiation documentation
Answer: A
Explanation:
Explanation
Reference http://prince2.wiki/Quality#The_Quality_Knowledge_provided_by_PRINCE2
NEW QUESTION # 90
Which is a purpose of the Project Product Description?
- A. Provide product cost input tothe Business Case
- B. Define the quality anticipated by the customer
- C. Define the key responsibilities for delivering product quality
- D. Provide information about the state of products
Answer: B
NEW QUESTION # 91
Which is a benefit of using PRINCE2?
- A. Prevents any changes once the scope of a project has been agreed
- B. Enables a Project Manager to be accountable for the success of a project
- C. Provides a defined structure of accountability, delegation, authority and communication
- D. Includes techniques for critical path analysis and earned value analysis
Answer: C
NEW QUESTION # 92
Which is a benefit of using PRINCE2?
- A. Avoids the need to involve corporate or programme management
- B. Can be applied to any type of project
- C. Enables the management of projects as well as of 'business as usual' activities
- D. Can be tailored by leaving out elements of the method for some projects
Answer: B
NEW QUESTION # 93
Which is part of quality control?
- A. Document the customer's quality expectations
- B. Write Product Descriptions
- C. Undertake quality reviews
- D. Provide assurance that the project is being conducted properly
Answer: C
NEW QUESTION # 94
Which is a purpose of the 'controlling a stage' process?
- A. To obtain approvals for products delivered in a work package
- B. To select and implement actions that will resolve deviations from a plan within tolerance
- C. To produce a team plan for the work to be assigned to a team manager
- D. To update a project plan to incorporate the actuals from a stage plan
Answer: B
Explanation:
Explanation
Reference http://prince2.wiki/Controlling_a_Stage#Purpose
NEW QUESTION # 95
Which is a purpose of the Controlling a Stage process?
- A. Produce a Team Plan for the work to be assigned to a Team Manager
- B. Obtain approvals for products delivered in aWork Package
- C. Update a Project Plan to incorporate the actuals from a Stage Plan
- D. Select and implement actions that will resolve deviations from a plan within tolerance
Answer: D
NEW QUESTION # 96
Which is a purpose of a Risk Register?
- A. Record how risk management activities will be undertaken on the project
- B. Capture issues which are impacting on the delivery of the project objectives
- C. Capture risks that may occur during the project
- D. Record the risk tolerance for the project
Answer: C
Explanation:
Section: Volume B
NEW QUESTION # 97
Which is a purpose of the Quality theme?
- A. Determine the communication needs of the organization's quality assurance function
- B. Identify all the products of the project to ensure the scope has been adequately defined
- C. Establish quality assurance to maintain the quality management system
- D. Establish how the project will ensure that all products created meet their requirements
Answer: D
NEW QUESTION # 98
Which role is part of the project management team?
- A. Change Authority
- B. Stakeholder
- C. Corporate or programme management
- D. Quality assurance
Answer: A
NEW QUESTION # 99
Identify the missing words in the following sentence.
A benefit of adopting PRINCE2 is that it can be applied to [ ? ] - and can easily be implemented alongside specialist techniques.
- A. all types of programmes
- B. business as usual
- C. programmes and projects
- D. any type of project
Answer: D
NEW QUESTION # 100
Which enables the project's products and all interdependencies to be clearly identified and documented?
- A. Product-based planning technique
- B. Quality Management Strategy
- C. Quality review technique
- D. Product breakdown structure
Answer: A
NEW QUESTION # 101
......
True PRINCE2-Foundation Exam Extraordinary Practice For the Exam: https://www.actual4exams.com/PRINCE2-Foundation-valid-dump.html
Get 100% Passing Success With True PRINCE2-Foundation Exam: https://drive.google.com/open?id=1i3sjJzHV2mqQkXzN_OH9cvMzI9YiDqZL