NEW QUESTION 20
Which of the following is a prerequisite for external refurbishment?
- A. Select the material group for externally refurbished materials.
- B. Define the order type for external refurbishment.
- C. Activate the subcontracting indicator in an external activity.
- D. Create the purchasing info record for the external provider.
Answer: C
NEW QUESTION 21
Which statements are correct about UI technologies in SAP S/4HANA Asset Management? Note: There are 2 correct Answers to this question.
- A. The cloud version can also use SAP GUI for Windows.
- B. SAP GUI transactions can be used in the SAP Fiori launchpad.
- C. Web Dynpro apps can be used in the SAP Fiori launchpad.
- D. SAP Fiori launchpad supports only SAPUI5 apps.
Answer: C,D
NEW QUESTION 22
Which statements regarding a maintenance order with status REL are correct? Note: There are 3 correct Answers to this question.
- A. The controller can determine actual cost surcharges.
- B. The planner can change planned costs at the operation level.
- C. Goods receipts for external services can be entered.
- D. The planner can change estimated costs only at the header level.
- E. Shop papers can be printed only after the order release.
Answer: B,C,E
NEW QUESTION 23
What happens if you change the primary key of a functional location?
- A. The functional location is immediately assigned to a new superior functional location when the new label is entered.
- B. The user must decide whether the functional location is assigned to a new superior functional location.
- C. Changing the superior functional location via alternative labeling is not possible.
- D. The user must define a new labelling system for the new primary key.
Answer: A
NEW QUESTION 24
Which SAP UI technology is used for the Report and Repair Malfunction app?
- A. SAPUI5
- B. Web Dynpro
- C. SAP GUI for HTML
- D. SAP GUI for Windows
Answer: B
NEW QUESTION 25
You want to create a maintenance order with an external order operation that includes service items.
Which of the following statements are correct? Note: There are 3 correct Answers to this question.
- A. The assignment of a control key with the service indicator set is mandatory.
- B. The usage of a model service specification is mandatory.
- C. The actual value entry can be recorded only via the service entry sheet.
- D. The assignment of a service master record is mandatory.
- E. The assignment of service master records to an order operation is optional.
Answer: A,C,D
NEW QUESTION 26
In which component do you have to perform most of the configuration to set up SAP Asset Manager?
- A. SAP S/4HANA
- B. SAP ERP on HANA
- C. SAP Mobile Platform
- D. SAP BTP (formerly Cloud Platform)
Answer: D
NEW QUESTION 27
Which steps are available for the maintenance technician when using the Report Malfunction tile? Note:
There are 3 correct Answers to this question.
- A. Select and print the maintenance order shop papers.
- B. Add a URL to provide further information.
- C. Display the current location of the technical object.
- D. Input estimated costs for repair malfunction.
- E. View details of the technical object by navigating to the Asset Viewer.
Answer: B,C,E
NEW QUESTION 28
Which statement is correct about the SAP Fiori tile group? Note: There are 2 correct Answers to this question.
- A. It is assigned via a portal role.
- B. It can be assigned directly to the user via personalization.
- C. It provides only SAPUI5-based apps.
- D. It is based on an SAP Fiori tile catalog.
Answer: C,D
NEW QUESTION 29
You want to see historical information relating to the phases when equipment was installed at a functional location. Where can you find this information?
- A. Location Analysis List
- B. Object Statistics
- C. Structure Display
- D. Usage List
Answer: D
NEW QUESTION 30
The maintenance engineer creates a strategy plan with the call object maintenance order. Shift factors are set to 100%. Which date is relevant for the calculation of future planned dates if the maintenance work is delayed?
- A. Actual finish date of the maintenance order
- B. Technical completion date of the maintenance order
- C. Planned date of the next call, independent of maintenance order dates
- D. Planned end date of the maintenance order
Answer: B
NEW QUESTION 31
The planner adds stock materials in the maintenance order. Which statements regarding reservations in maintenance orders are correct? Note: There are 2 correct Answers to this question.
- A. All open reservations are closed when the maintenance order is set to TECO.
- B. Reservations are created only after a material availability check has been performed.
- C. Open reservations can be cleared when a maintenance order operation is finally confirmed.
- D. For the combination of order type and planner group, you can decide when reservations are created.
Answer: A,C
NEW QUESTION 32
What is the correct receiver object type for the settlement of a refurbishment order?
- A. The WBS element
- B. The fixed asset
- C. The cost center
- D. The material
Answer: D
NEW QUESTION 33
Which functions are available in the Resource Scheduling for Maintenance Planners app? Note: There are 2 correct Answers to this question.
- A. Schedule and dispatch maintenance operations by shifts.
- B. Cancel dispatched maintenance order operations.
- C. Monitor maintenance order operations due in the next 4 weeks.
- D. Print job papers from a maintenance order.
Answer: B,C
NEW QUESTION 34
Which of the following are components of cloud-based SAP Intelligent Asset Management? Note: There are 2 correct Answers to this question.
- A. SAP Work Manager
- B. SAP Asset Manager
- C. Worker Safety applications
- D. SAP Predictive Asset Insights
Answer: B,D
NEW QUESTION 35
Which functionalities belong to the current portfolio of SAP BusinessObjects Business Intelligence?
Note: There are 2 correct Answers to this question.
- A. SAP Lumira
- B. SAP QuickViewer
- C. Plant Maintenance Information Systems (PMIS)
- D. SAP Crystal Reports
Answer: A,D
NEW QUESTION 36
The maintenance technician wants to document work steps for a technical object in a notification. What are the best options to be used in regard to code-based reporting? Note: There are 2 correct Answers to this question.
- A. An entry in the object list
- B. An activity in the notification header
- C. A task in the notification item
- D. A text in the subject long text screen
Answer: B
NEW QUESTION 37
Which of the following are standard functionalities of SAP Asset Manager? Note: There are 3 correct Answers to this question.
- A. Work orders and operations
- B. Cost analytics
- C. Breakdown analytics
- D. Technical objects
- E. ESRI maps
Answer: A,D,E
NEW QUESTION 38
You want to set up a general maintenance task list for inspection rounds using the overall time confirmation as a simplified way to record measurement documents. What do you need to do? Note:
There are 2 correct Answers to this question.
- A. Assign a piece of equipment with an allocated measuring point to a task list operation.
- B. Assign an inspection lot to the task list header.
- C. Assign a measuring point as a production resources/tools (PRT) to a task list operation.
- D. Assign an inspection document as a PRT to the task list operation.
Answer: A,C
NEW QUESTION 39
Which of the following parameters are available when you define a new maintenance plan category?
Note: There are 3 correct Answers to this question.
- A. Order type
- B. Call object
- C. Maintenance activity type
- D. Completion date
- E. Change documents
Answer: B,D,E
NEW QUESTION 40
In which cases are projects (PS) used in the area of SAP S/4HANA Asset Management? Note: There are 2 correct Answers to this question.
- A. Shutdowns and overhaul
- B. External refurbishment
- C. Condition-based maintenance
- D. Investments
Answer: A,D
NEW QUESTION 41
You want to set up a scenario for regular maintenance. The first event should take place after 1 year; after that, it is a regular cycle of 6 months. Which parameter do you have to use to map this in the system?
- A. Shift factor
- B. Maintenance plan category
- C. Scheduling indicator
- D. Maintenance package offset
Answer: D
NEW QUESTION 42
......
SAP C_TS413_2020 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Refurbishment of Spare Parts < 8% | Describe and implement the process of internal and external refurbishment of spare parts. |
| Preventive Maintenance > 12% | Describe the options for preventive maintenance using task lists, single-cycle, time-based strategy and performance-based strategy maintenance plans. |
| Corrective Maintenance > 12% | Describe and implement the process of corrective maintenance using traditional and FIORI-based applications. |
| User Interface and User Experience < 8% | Descibe UI technologies and client types used with SAP S/4HANA Asset Management. |
| Organizational Units and Master Data 8% - 12% | Describe and implement the necessary organizational units especially regarding the integration into the general logistics and accounting units. |
| Breakdown Maintenance < 8% | Describe and implement the process of breakdown maintenance using traditional and FIORI-based applications. |
| Mobile Maintenance < 8% | Describe the available mobile applications for SAP S/4HANA Asset Management |
| Technical Objects > 12% | Describe and implement technical asset structures following fundamental concepts and building the integration to key neighbour applications. |
| Analytics < 8% | Describe and implement the options for analytics in asset management especially regarding S/4HANA emebedded analytics. |