PRINCE2 Agile Foundation certification is ideal for individuals who are involved in projects that require the use of both PRINCE2 and agile methodologies. It demonstrates that they have a good understanding of the PRINCE2 framework and how to apply it in an agile environment. PRINCE2 Agile Foundation certification is recognized globally and can help individuals to advance their careers in project management. It is also a valuable asset for organizations that want to ensure their project managers have the necessary skills and knowledge to manage projects effectively using PRINCE2 Agile.

 

NEW QUESTION # 37
Which statement about the waterfall methodology definition is CORRECT?

  • A. It is a behavior that involves making things transparent
  • B. It promotes the use of experiments carried out in a scientific way
  • C. It states that deadlines should not be moved
  • D. It has distinct goals for each stage of development

Answer: D


NEW QUESTION # 38
Which is a purpose of the 'managing product delivery' process?

  • A. To plan the delivery of the products before committing to significant expenditure
  • B. To agree on what is required for accepting, executing and delivering project work.
  • C. To delegate day-to-day management of the project to the project manager
  • D. To establish and deliver the project communications to the wider organization

Answer: B


NEW QUESTION # 39
During which process should release planning be done for the FIRST time?

  • A. Controlling a stage
  • B. Managing a stage boundary
  • C. Initiating a project
  • D. Managing product delivery

Answer: B


NEW QUESTION # 40
Which statement about the 'keep teams stable' target is CORRECT?

  • A. It ensures that the level of quality is protected
  • B. It will lead to a lower cost of ownership
  • C. It is required in order to allow the team to self-organize
  • D. It results in the earth delivery of a minimum viable product

Answer: C


NEW QUESTION # 41
What is the MOST LIKELY benefit from frequent releases into operational use?

  • A. The risks associated with agile ways of working are assessed
  • B. Feedback is obtained from real customers
  • C. The need for configuration management is reduced
  • D. The need for customer involvement is increased

Answer: B


NEW QUESTION # 42
Which is a benefit of the Lean Startup approach to releasing a product?

  • A. It provides quick feedback that can be responded to at the earliest opportunity
  • B. It reduces the number of people needed to manage a release of a product
  • C. It provide a technique to reduce the testing of a product before release
  • D. It enables the release plans to be synchronized with the PRINCE2 plans

Answer: D


NEW QUESTION # 43
What is an epic?

  • A. A high-level requirement
  • B. A detailed feature
  • C. A low-level requirement
  • D. A fine-grained user story

Answer: A


NEW QUESTION # 44
Which statement about the 'directing a project' process is CORRECT?

  • A. The project board should make decisions based on the Agilometer risks
  • B. The project board should increase the stage-level time tolerance
  • C. A project board member should fulfill the product owner role within a delivery team
  • D. The project board should attend regular project progress meetings

Answer: C


NEW QUESTION # 45
Why is Lean Startup included in the 'starting up a project' process in PRINCE2 Agile?

  • A. Because it is designed to manage projects, delivering products in timeboxes
  • B. Because it enables agile to be used in challenging and uncertain situations
  • C. Because running a project and setting up a new business are the same
  • D. Because it explains how a small company can grow using traditional technologies

Answer: B


NEW QUESTION # 46
How does PRINCE2 Agile describe Scrum?

  • A. Scrum is the most well-known agile framework
  • B. Scrum is agile and agile is Scrum
  • C. Scrum is an IT method
  • D. Scrum is a project management framework

Answer: A


NEW QUESTION # 47
Whose interests are specifically represented by the senior supplier?
1. Those ensuring the project is value for money.
2. Those who will use the project's products.
3. Those who will be developing the project's products.
4. Those responsible for the project's technical integrity.

  • A. 1 and 2
  • B. 1 and 4
  • C. 3 and 4
  • D. 2 and 3

Answer: C


NEW QUESTION # 48
Which statement about the 'directing a project' process is CORRECT?

  • A. The project board should receive regular reports focusing on cost and time overruns
  • B. The project board should attend the delivery team's daily stand up meeting
  • C. The project board may pull reports from the information radiator
  • D. As a minimum, the project board should receive oral reports from the project manager

Answer: C


NEW QUESTION # 49
Which statement about the 'be on time and hit deadlines' target is CORRECT?

  • A. It ensures that the level of quality is protected
  • B. It is achieved by keeping the delivery teams stable
  • C. It helps with planning dependencies within a project
  • D. It allows change to be handled dynamically

Answer: C


NEW QUESTION # 50
Which PRINCE2 principle should be followed in order to engage the business, user and supplier stakeholder interests?

  • A. Defined roles and responsibilities
  • B. Continued business justification
  • C. Tailor to suit the project
  • D. Learn from experience

Answer: A


NEW QUESTION # 51
Which is an advantage of frequent releases?

  • A. The delivery team becomes more experienced at product handover
  • B. A 'one-team' culture in the project team is encouraged
  • C. Releases can be used to replace management stages
  • D. Configuration management becomes less important

Answer: A


NEW QUESTION # 52
Which statement about the 'initiating a project' process is CORRECT?

  • A. The process should take more time than usual for disruptive projects
  • B. The initiation stage plan should form part of the project plan
  • C. The project solution should be documented in detail in the project product description
  • D. The impact of frequent releases on quality management should be assessed

Answer: D


NEW QUESTION # 53
Which statement explains how the 'learn from experience' principle is applied in an agile context?

  • A. It integrates releases within management stages
  • B. It provides guidance on mapping PRINCE2 roles to an agile environment
  • C. It is supported by the 'inspect and adapt' concept
  • D. It focuses on the prioritization and decomposition of requirements

Answer: C


NEW QUESTION # 54
In Scrum, what answers the question 'what can be done this sprint?'

  • A. Sprint review
  • B. Increment
  • C. Sprint planning
  • D. Daily scrum

Answer: D


NEW QUESTION # 55
Which statement about the 'protect the level of quality' target is CORRECT?

  • A. It is achieved by ensuring that all features are delivered
  • B. It is unlikely to be achieved if incomplete user documentation is provided
  • C. It avoids the use of extra people to improve progress during a timebox
  • D. It allows change at the detailed level to be handled dynamically

Answer: A


NEW QUESTION # 56
What is typically added to a user story as the understanding of the requirement evolves?

  • A. Definition of 'ready'
  • B. Acceptance criteria
  • C. An epic
  • D. Effort actually expended

Answer: B


NEW QUESTION # 57
What information is NOT typically displayed on a burn chart?

  • A. Team working agreements
  • B. Amount of time elapsed
  • C. Effort remaining
  • D. Actual amount of work done

Answer: A


NEW QUESTION # 58
Which statement explains the target 'be on time and hit deadlines' for flexible delivery?

  • A. It sets the project baseline at the correct level
  • B. It reduces testing in order to meet deadlines
  • C. It enables team dynamics to remain the same
  • D. It improves the supplier's reputation with the customer

Answer: B


NEW QUESTION # 59
Which statement BEST describes the PRINCE2 Agile guidance for change?

  • A. The executive should approve delivery level changes to harness the benefits of positive change
  • B. The executive should manage changes dynamically at the detailed level
  • C. The delivery team should quickly approve changes to the project baseline
  • D. The delivery team should be authorized to make changes at the detailed level

Answer: D